There are several construction projects in various stages of completion in the City of Stephenville. Please see the list below of some current and upcoming Public Works projects to find out where work could be happening in your area.

The links in the project descriptions below provide maps with highlighted work areas. Note: Some maps are not exact and are for general location purposes only. Further information is located in the actual contract specifications.

Current Projects up for bid:

Water Well Field Development Project – The City of Stephenville (City) plans to enter into an agreement with a Professional Engineering Services firm and is seeking Statements of Qualifications (SOQ) from firms whose combination of resources, experience, and expertise will provide capable and timely professional services to the City of Stephenville. Please see the

The City of Stephenville is always conscious and extremely appreciative of the respondent’s efforts and time investment in the preparation of submittal information. The City will receive Qualification Statements at Stephenville City Hall until 5 pm Friday, June 1, 2018. Information related to this solicitation, including any addenda, will be located here and the map showing the project location.

For questions related to this Request for Qualifications (RFQ), contact:

City of Stephenville
Nick Williams, P.E., CFM, Director Public Works, or
Eugene Calvert, P.E., PTOE, City Engineer
298 West Washington Street,
Stephenville Texas 76401
254.918.1201/254.918.1223; gcalvert@stephenvilletx.gov  or nwilliams@stephenvilletx.gov

Current Projects:

2018 Street Maintenance – Chip Seal Project – bids were opened on November 29, 2017, and was awarded by the city council to Jay Mills Contracting at the December 5, 2017 council meeting. Work will begin in the early spring of 2018. Please see the attached map and street listing for the current project.

2018 Micro-Surfacing Program –  bids were opened December 20, 2017 and was awarded by the city council to Intermountain Slurry Seal January 2, 2018 council meeting. Work will begin in early spring of 2018. Please see the attached Street Listing & Map for current project information.

2018 Professional Engineering Services – The City of Stephenville is seeking to contract with a firm to provide Professional Engineering Services for a 750,000 Gallon Garfield Ground Storage Tank Rehabilitation Project based on the evaluation completed on February 9, 2015.  For the photos of the report, Group 1-20, Group 21-40, Group 41-60, Group 61-80. The Stephenville city council met on May 1, 2018 and approved the services agreement for Tank Industries Consultants and Heart of Texas Inspection Services.

2018 Professional Engineering Services – The City of Stephenville (City) plans to contract with up to three (3) firms to provide Professional Engineering Services (Services) for Various Storm Drainage Improvement Projects (Projects) and Utility and Pavement Engineer of Record. The Stephenville city council met on May 1, 2018 and approved the services agreement for Freese and Nichols for the Spring Bouquet Drainage Study.

Eastside Sewer – Please follow link here for project information.

Completed Projects:

2017/18 Texas Community Development Block Grant (TxCDBG) – As of the January 3, 2017, Administrative/Professional Services for the RFQ have been awarded to Public Management, Inc.  The Engineering Services for the RFQ have been awarded to Pacheco Koch, LLC. The advertisement was posted online and also in the Empire Tribune on November 22, 2016. If you need further information, please call Sara Tankersley at 254-918-1292.  The project was completed $25,974.51 or approximately 5.1% under budgeted construction costs and was accepted by the city council at the December 5, 2017 council meeting.

2017 Long Street Low Water Crossing Repair Project – Cruz Hernandez Construction – performed the removal and replacement of concrete, asphalt riprap, installation of supporting embankment and reinforced concrete riprap for the Long Street Low Water Crossing Repair Project (Location Map)within the City of Stephenville.

2017 W. Frey Street and Ollie Avenue – Utility work completed to correct  Please see Customer Notification form and map.

2017 Long Street Low Water Crossing Repair Project – Cruz Hernandez Construction – for removal and replacement of concrete, asphalt riprap, install supporting embankment and install reinforced concrete riprap for the Long Street Low Water Crossing Repair Project (Location Map) within the City of Stephenville.

2016-17 Texas Community Development Block Grant (TxCDBG) Water Line Improvement Project – as of December 5, 2017 – Council accepted the  project completed by B & L Construction along West Elm Street between North Ollie and Clinton Avenue and along West Oak Street between North Ollie Street and North Race Street (location map) within the City of Stephenville. As of November 4, 2016 awarded to Public Management (Administrative) and Pacheco Koch, LLC (Engineering). Exhibit A – Performance Statement, Exhibit B – Project Budget.

2017 – Concrete Curb and Gutter repair work is taking place on Ben Hogan Drive, Prairie Wind, Midnight Shadow, Glenwood and at a Bosque River Trail head parking area on Graham Street.

2017 Pavement Maintenance – Micro-Surfacing Project – as of May 2, 2017 – Viking Construction, Inc. – micro-surface paving various streets (location map) within the City of Stephenville.

2017 Pavement Maintenance – Chip Seal Project – as of May 2, 2017 – Rose Contracting Company –  The chip seal application of emulsified asphalt, cover coat aggregate and fog seal to various streets (location map) within the City of Stephenville.

2016 Methodist Branch Sanitary Sewer Relief Line Project –  B & L Construction 2016 TSU Methodist Branch Sanitary Sewer Relief Line Project – Location Map Notice to Residents – Under bid by $203,409.50.

2016-17 Pavement Maintenance – Inglewood Drive Street Resurfacing – Jay Mills Contracting 2016 Pavement Maintenance Inglewood Drive Street Resurfacing – Location Map

2016 Pavement Maintenance – Crack Sealing –  Four B Paving, Inc. 2016 Crack Sealing Project Overview

2016 City Park Parking Lot – Jay Mills Contracting.

2016 City Park Low Water Crossing – Jay Mills Contracting.

2016 Concrete Maintenance – Alexander Road near Counts – Pro-Foundation Technology.

2016 Pavement Maintenance – Micro-Surfacing –  Intermountain Slurry Seal, Inc. Micro-surfacing – Street Listing Micro-Surfacing Overview Map

2016 Pavement Maintenance – Chip Seal – Brett Construction – Completed Project Status as of September 30, 2016. Chip Seal Whole City Overview